Latest update on Hull’s planned roadworks

CATEGORIES
TAGS

Share:

Share on facebook
Share on twitter
Share on pinterest
Share on linkedin
Share on reddit
Share on whatsapp

This week it was announced that Northern Powergrid would be carrying out essential upgrades to the electricity network in Wincolmlee.

The work will begin on Monday January 31 and could last up to five weeks, during which period the road will be closed in both directions between Wilmington Bridge and Air Street.

Cllr Dean Kirk, portfolio holder for roads, highways and transport said: “Northern Powergrid has advised us that these upgrades are necessary to ensure the electricity network continues to operate reliably and safely.”

Advertisement

Read the full story

Below is a breakdown of roadworks taking place across Hull over the next few weeks:

Sponsored Listings

Sun 6 Feb @ 4:00pm – 11:00pm
LocationStart DateDue DateReasonUtility/HCC Name
A63 improvement scheme – Commercial Road26/10/2130/4/22Enable H&S and safe systems of works for operatives working on the schemeNational Highways
A63 improvement scheme –  St James Street to Market place1/5/201/5/25Lane closures and local diversions until completion of scheme. LGV diversion signed via ERYC to limit number of LGVs in city centre.National Highways
A63 improvement scheme – Daltry Street to Rodger Milward Way24/1/224/2/22Road closed overnight from 8pm – 6am (Mon- Fri nights)National Highways
Barham Road29/11/216/2/22Carriageway resurfacing and concrete repairs.HCC – MP&I
Bellfield Avenue10/1/2211/4/22Multi-way signals at the junction with Savoy Road. Manned between traffic sensitive times.HCC – MP&I
Beverley Road – Brunswick Arcade4/10/211/9/22Brunswick Arcade demolition. Contraflow in place until April 2022. Lane closure in place until Sept 2022.HCC – MP&I
Beverley Road – Mizzen Road to Windle Avenue4/1/2211/2/22Construction of new cycle track and footpath on the existing footpath and verge. Lane closure.MP&I ARBPMLTD
Eglinton Avenue21/2/224/3/22Road closure due to gas mains replacement on Ings Road.Northern Gas Network
Hessle Road (12-month Scheme)23/8/214/9/22Footway reconstruction.HCC – MP&I
Holderness Road (Victor St to Southcoates) (PHASES 1-8)4/1/2211/9/22Full footway reconstruction scheme.MP&I – Highways Strategy & Design
Holderness Road – Holland Street to Sherburn Street4/1/2213/2/22Footway reconstruction and repaving.MP & I
Holderness Road24/1/2211/2/22Excavate and locate cable, joint new cable and reinstate excavations for new connection.SWB MASS MARKET Z3
Humber Street7/2/2219/3/22Installation of bollards. Works span width of footway and carriageway outside Dinostar. Work will be done in sections to maintain pedestrian walkway.HCC – MP&I
Ings Road14/2/2211/3/22Works to footway and carriageway.Northern Gas Network
Leads Road17/1/2221/1/22Affecting Truro Close junction, repairs to road.MS3 Networks Ltd
Lowgate Footway Repair Scheme – West Footway22/10/2131/1/22Work delayed due to signal failure on A63. Northbound road closure 24/7. Work taking place 7.30am-6pm Monday to Saturday. TM taken off in conjunction with A63 closures.HCC – MP&I
Lowgate Footway Repair Scheme – East Footway31/1/2210/4/22Work delayed due to signal failure on A63. Southbound road closure 24/7. Work taking place 7.30am-6pm Monday to Saturday. TM taken off in conjunction with A63 closures.HCC – MP&I
Portland Place4/1/2221/1/22Essential gas repairs. Road closure, traffic to follow diversion.Northern Gas Network
Priory WayFeb-2022Feb-2023Major widening and construction of three signalised junctions.HCC – MP&I
Rawling Way10/1/2217/1/22Resurfacing and concrete repairs. Closure between 7.30pm and 6am.HCC – MP&I
Savoy Road14/2/223/3/22Road closure due to gas mains replacement on Ings Road.Northern Gas Network
Silver Street4/1/2231/1/22Road closure due to installation of automated bollards.HCC – MP&I
Stoneferry Rd Scheme – Woodhall Street to Lorraine Avenue1/4/2128/5/22Major Improvement Scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completedHCC – MP&I
Stoneferry Rd Scheme – Chamberlain Road to Bandstand roundabout23/4/2125/6/22Major improvement scheme commissioned by HCC  – Infrastructure improvements and road widening. Lane closures throughout the scheme. Signals works at Woodhall street junction are now completedHCC – MP&I  COLAS
Stoneferry Rd SchemeFeb-2022Feb-2022Resurfacing to mainline carriageway at the Ferry Lane roundabout. Overnight road closure.HCC – MP&I  COLAS
Sutton Road21/1/2222/1/22Minor, non-excavation works near Stockholm Road junction (Footway). Cherry picker to access telecoms mast for testing / maintenance works. 7.30pm – 5am.  Illuminated Stop / Go boards.O2
Wincolmlee (Phase 1)13/12/2117/1/22Essential work to upgrade power supply. Multi-way signals, to be manned during traffic-sensitive times.Northern Powergrid
Wincolmlee (Phase 2)31/1/224/3/22New connection and cable upgrades. Road closure.Northern Powergrid

Hull's FREE weekly newsletter

A weekly round-up of Hull news, great events and things to do.

Got something to share?

We want to share everything positive that’s going on around Hull. We have loads of great ways to share your stuff:
Click the button above or email us at events@hullwhatson.com
*Registration required
Featured Hull Events
Sun 6 Feb @ 4:00pm – 11:00pm
Wed 2 Feb @ 7:00pm – 10:30pm
Places you should visit
Unmissable offers!
Available
Sat 1 Jan – Mon 31 Jan
Available
Wed 11 Aug – Mon 31 Jan
Available
Thu 23 Dec – Mon 31 Jan